[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937976":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":23},937976,606,1,"单选题","（2017年真题）某工程项目实施过程的部分时间参数如下表所示： 其中，总时差最大的活动是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","B",false,{"key":13,"text":16,"correct":17},"D",true,{"key":19,"text":20,"correct":14},"C","E",{"key":16,"text":22,"correct":14},"G","本题考查的是制定进度计划的方法。根据总时差的计算公式：TFi-j=LSi-j-ESi-j，各个活动的总时差为：B 为15-10=5；D 为39-31=8；E为20-20=0；G 为4-0=4。故D 活动的总时差最大。",{"id":6,"name":25,"category":26,"favorite":27},"工程项目组织与管理","建筑工程",0]