[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937970":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937970,606,1,"单选题","（2008年真题）某双代号网络计划如下图所示，工作 D 的总时差和自由时差分别为( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1天和1天",false,{"key":16,"text":17,"correct":14},"B","1天和2天",{"key":19,"text":20,"correct":14},"C","2天和l天",{"key":22,"text":23,"correct":24},"D","2天和2天",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]