[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937969":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},937969,606,1,"单选题","（2007年真题）M 工作有 2 个紧前工作，其持续时间分别是 6 天和 10 天，最早开工时间分别为第 15 天和第 20 天，则 M 工作的最早开始时间为第( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30",true,{"key":16,"text":17,"correct":18},"B","26",false,{"key":20,"text":21,"correct":18},"C","25",{"key":23,"text":24,"correct":18},"D","21","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]