[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937968":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937968,606,1,"单选题","（2009年真题）某分部工程双代号时标网络计划如图 9－16 所示，则工作 B 的总时差和自由时差分别是( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0天，0天",false,{"key":16,"text":17,"correct":18},"B","2天，0天",true,{"key":20,"text":21,"correct":14},"C","2天，2天",{"key":23,"text":24,"correct":14},"D","4天，0天","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]