[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937967,606,1,"单选题","（2013年真题）某工程双代号时标网络计划如下图所示，其中工作 B 和 E 的总时差和自由时差分别为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1周和1周；1周和1周",false,{"key":16,"text":17,"correct":18},"B","3周和1周；2周和1周",true,{"key":20,"text":21,"correct":14},"C","3周和3周；2周，0周",{"key":23,"text":24,"correct":14},"D","4周和3周；3周和2周","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]