[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937966":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937966,606,1,"单选题","（2011年真题）工程项目进度管理中，计划评审技术对时间的估算采用( )估算方法。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总时间",false,{"key":16,"text":17,"correct":14},"B","最大可能时间",{"key":19,"text":20,"correct":14},"C","阶段时间",{"key":22,"text":23,"correct":24},"D","加权平均时间",true,"计划评审技术——是计划中工作与工作之间的逻辑关系肯定，但每项工作的持续时间不肯定，一般采用加权平均时间估算，并对按期完成项目的可能性做出评价的网络计划方法。 PERT 与 CPM 的根本区别在于它使用了加权平均时间估算，做出来的进度安排计划要比 CPM 使用最大可能估算做出的现实。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]