[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937962":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},937962,606,1,"单选题","（2016年真题）工程项目进度管理中，可以称为软逻辑关系的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织关系",true,{"key":16,"text":17,"correct":18},"B","工艺关系",false,{"key":20,"text":21,"correct":18},"C","时间关系",{"key":23,"text":24,"correct":18},"D","工序关系","工作之间由于组织安排需要或资源调配需要而规定的先后／顺序关系叫组织关系。 组织关系也称为软逻辑关系，软逻辑关系可以由项目团队确定。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]