[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937961":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937961,606,1,"单选题","（2016年真题）偏差对后续工期的影响通常需要借助网络计划进行判断，根据该项目是否处于关键线路、其进度偏差是否超过该项工作的( )来判断。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","最早开始时间",false,{"key":16,"text":17,"correct":14},"B","最迟开始时间",{"key":19,"text":20,"correct":14},"C","总时差和总工期",{"key":22,"text":23,"correct":24},"D","总时差和自由时差",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]