[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937960":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937960,606,1,"单选题","（2014年真题）工程双代号时标网络计划如图所示，当计划执行到第 5 周末检查时，其实际进度如图中前锋线所示，检查结果表明( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","D工作滞后1周，不影响总工期",false,{"key":16,"text":17,"correct":14},"B","I工作滞后1周，预计总工期延长1周",{"key":19,"text":20,"correct":14},"C","E工作提前1周，预计总工期缩短1周",{"key":22,"text":23,"correct":24},"D","H工作提前1周，不影响总工期",true,"H 工作在非关键线路上，提前 1 周，不影响总工期",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]