[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937959":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937959,606,1,"单选题","（2010年真题）在工程项目进度资源优化管理中，影响进度的主要因素是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","资源的需求情况",false,{"key":16,"text":17,"correct":14},"B","资源的配置情况",{"key":19,"text":20,"correct":14},"C","资源的利用情况",{"key":22,"text":23,"correct":24},"D","资源的供应情况",true,"资源的供应情况是影响工程进度的主要因素。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]