[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937958":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937958,606,1,"单选题","（2014年真题）某工程拟将持续时间由 15 天缩短为 13 天，持续时间为 15 天时总费用为 10 万元，其中直接费用为 8 万元，持续时间为 13 天时直接费用为 10 万元。缩短持续时间的间接费用率为 0.1 万元\u002F天，则工程持续时间缩短后总费用为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","12.0万元",false,{"key":16,"text":17,"correct":14},"B","11.1万元",{"key":19,"text":20,"correct":21},"C","11.8万元",true,{"key":23,"text":24,"correct":14},"D","10.2万元","工程持续时间缩短后总费用=工程持续时间为 15 天时总费用+工程持续时间缩短后增加的直接费-工程持续时间缩短后减少的间接费=10+(10-8)-2×0.1=11.8 万元。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]