[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937957":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937957,606,1,"单选题","（2018年真题）工程网络计划的工期优化是通过( )，使计算工期满足要求工期。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","改变关键工作之间的逻辑关系",false,{"key":16,"text":17,"correct":14},"B","将关键工作压缩成非关键工作",{"key":19,"text":20,"correct":14},"C","压缩直接费最小的工作的持续时间",{"key":22,"text":23,"correct":24},"D","压缩关键工作的持续时间",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]