[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937956":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937956,606,1,"单选题","（2010年真题）某工程网络计划中，N 工作的最早开始时间和最早完成时间分别为第 5 天和第 7 天，最迟开始时间和最迟完成时间分别为第 8 天和第 10 天，则 N 工作的总时差是( )天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","2","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]