[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937955":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937955,606,1,"单选题","（2016年真题）某工作网络计划中，N 工作的最早开始时间和最早完成时间分别为第 5 天和第 8 天，最迟开始时间和最迟完成时间分别为第 7 天和第 10 天，则工作 N 的总时差为( )天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","3",{"key":22,"text":23,"correct":24},"D","2",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]