[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937952":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937952,606,1,"单选题","（2005年真题）在双代号或单代号网络计划中，判别为关键工作的条件是该工作( C )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","自由时差最小",false,{"key":16,"text":17,"correct":14},"B","与其紧后工作之间的时间间隔为零",{"key":19,"text":20,"correct":21},"C","最迟开始与最早开始时间的差值最小",true,{"key":23,"text":24,"correct":14},"D","资源消耗最多","双代号网络图中时间参数的计算 (1)关键工作。 总时差最小的工作是关键工作 。 (2)关键线路。 自始至终全部由关键工作组成的线路为关键线路，或线路上总的持续时间最长的线路为关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]