[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937951":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937951,606,1,"单选题","（2017年真题）估算工作时间的模拟法最常用的是( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","类似模拟法",false,{"key":16,"text":17,"correct":14},"B","数字模拟法",{"key":19,"text":20,"correct":21},"C","蒙特卡罗分析法",true,{"key":23,"text":24,"correct":14},"D","情景模拟法","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]