[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937947":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937947,606,1,"单选题","（2011年真题）工程项目进度管理中，工作定义的主要任务是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","制订出完成各项具体工作的时间进度安排",false,{"key":16,"text":17,"correct":14},"B","对完成各项具体工作所需要的时间进行估计推算",{"key":19,"text":20,"correct":14},"C","找出各项具体工作之问的逻辑关系并形成文件",{"key":22,"text":23,"correct":24},"D","确定为产生各项可交付成果必须进行的具体工作",true,"工作定义 ——就是对工作分解结构(WBS)中规定的可交付成果或半成品所产生的必须进行的具体工作进行定义，并形成相应的文件，包括： ①工作清单和②工作分解结构的更新",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]