[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937946,606,1,"单选题","（2014年真题） 工程项目工作定义的基本依据是( )中做出的工作分解结构(WBS)",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度管理",false,{"key":16,"text":17,"correct":14},"B","合同管理",{"key":19,"text":20,"correct":14},"C","工程管理",{"key":22,"text":23,"correct":24},"D","范围管理",true,"范围管理中作出的 WBS 是工作定义的基本依据。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]