[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937945":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937945,606,1,"单选题","（2013年真题）双代号网络计划中，关键工作是指( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自由时差最小的工作",false,{"key":16,"text":17,"correct":14},"B","两端节点均为关键节点的工作",{"key":19,"text":20,"correct":14},"C","持续时间最长的工作",{"key":22,"text":23,"correct":24},"D","最迟完成时间与最早完成时间的相差最小的工作",true,"双代号网络图中时间参数的计算 (1)关键工作。 总时差最小的工作是关键工作 。 (2)关键线路。 自始至终全部由关键工作组成的线路为关键线路，或线路上总的持续时间最长的线路为关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]