[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937936":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937936,606,2,"多选题","（2017年真题）根据《标准施工招标文件》 (2007 年版)，下列关于隐蔽工程检查的说法，错误的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","承包人自检确定隐蔽工程具备覆盖条件的，应通知监理人在约定的期限内检查",false,{"key":16,"text":17,"correct":14},"B","监理人检查隐蔽工程发现质量不合格的，承包人应自费完成修复",{"key":19,"text":20,"correct":14},"C","监理人未按时进行检查也未提出延期要求的，视为隐蔽工程检查合格",{"key":22,"text":23,"correct":24},"D","监理人检查完毕且承包人覆盖隐蔽工程后，监理人不能再要求对隐蔽工程进行重新检查",true,{"key":26,"text":27,"correct":24},"E","承包人私自将隐蔽工程覆盖的，监理人有权指示承包人揭开检查，如果质量合格，由此增加的费用由发包人承担","DE","",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]