[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937931":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937931,606,2,"多选题","（2017年真题）根据FIDIC 施工合同条件，下列关于工程质量管理条款的说法，错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人应建立有效的质量管理体系，保证施工符合合同要求",false,{"key":16,"text":17,"correct":18},"B","按照工程师认可的质量管理体系施工，发生质量事故由业主承担责任",true,{"key":20,"text":21,"correct":14},"C","业主对图纸资料的真实性和正确性负责，承包人对自己的理解或推论负责",{"key":23,"text":24,"correct":18},"D","发生合同规定之外的检查和试验，由业主承担费用",{"key":26,"text":27,"correct":14},"E","承包人使用的施工设备影响了工程进度时，承包人应自费增加或更换施工设备","BD","选项B，正确的说法应为“保证工程质量是承包商的基本义务，遵照工程师认可的质量体系施工，并不能解除其依据合同应承担的任何职责、义务和责任”；选项D，正确的说法应为“由于额外检验和试验是基准日前承包商无法合理预见的情况，如果影响到的费用和工期，则视检验结果是否合格划分责任归属”。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]