[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937925":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937925,606,2,"多选题","（2013年真题）关于FIDIC《施工合同条件》指定分包商的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","指定分包商由业主选定",true,{"key":16,"text":17,"correct":14},"B","在承包商确定后才选择指定分包商",{"key":19,"text":20,"correct":21},"C","指定分包商与业主直接签订分包合同",false,{"key":23,"text":24,"correct":14},"D","对指定分包商的管理纳入承包商的管理之中",{"key":26,"text":27,"correct":14},"E","指定分包商是完成某项特定工作内容的特殊分包商","ABDE","指定分包商是由业主（或工程师）指定完成某项特定工作内容，并与承包商签订分包合同的特殊分包商。通用条件规定，业主有权将部分工程项目的施工任务或涉及提供材料、设备、服务等工作内容发包给指定分包商实施，指定分包与一般分包处于同等地位，工程师对其监督、协调工作应纳入对承包商的管理之中。@##",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]