[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937923":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937923,606,2,"多选题","（2017年真题）根据《标准施工招标文件》 (2007 年版)，下列情形中，应由发包人承担由此增加的费用并支付承包人合理利润的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","在施工现场遇到不可预见的地质条件",false,{"key":16,"text":17,"correct":18},"B","提供图纸延误",true,{"key":20,"text":21,"correct":18},"C","未按合同约定及时支付预付款、进度款",{"key":23,"text":24,"correct":18},"D","增加合同工作内容",{"key":26,"text":27,"correct":14},"E","异常恶劣的气候条件造成工程暂停","BCD","在履行合同过程中，由于发包人的下列原因造成工期延误的， 承包人有权要求发包人延长工期和(或)增加费用，并支付合理利润。 (1)增加合同工作内容； (2)改变合同中任何一项工作的质量要求或其他特性； (3)发包人迟延提供材料、工程设备或变更交货地点的； (4)因发包人原因导致的暂停施工； (5)提供图纸延误； (6)未按合同约定及时支付预付款、进度款； (7)发包人造成工期延误的其他原因。 由于出现合同约定的异常恶劣气候的条件导致工期延误的，承包人有权要求发包人延长工期。@##",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]