[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937907":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937907,606,1,"单选题","（2014年真题）根据《标准施工招标文件》 (2007年版)，合同进度计划是指经( )批准的施工进度计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监督人",false,{"key":16,"text":17,"correct":14},"B","承包人",{"key":19,"text":20,"correct":21},"C","监理人",true,{"key":23,"text":24,"correct":14},"D","投资人","合同进度计划的编制。 承包人应按合同约定的内容和期限， 编制详细的施工进度计划和施工方案说明报送监理人。 监理人应在合同约定的期限内批复或提出修改意见， 否则该进度计划视为已得到批准。 经监理人批准的施工进度计划称合同进度计划，是控制合同工程进度的依据",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]