[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937900,606,1,"单选题","（2010年真题）FIDIC 合同条件规定，争端裁决委员会作出裁决后( )日内任何一方未提出不满意裁决的通知，此裁决即为最终决定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":18},"B","28",true,{"key":20,"text":21,"correct":14},"C","56",{"key":23,"text":24,"correct":14},"D","84","提交争端裁决委员会决定。 裁决委员会应在收到提交的争议文件后 84 天内做出合理的裁决。做出裁决后的 28 天内任何一方未提出不满意裁决的通知，则此裁决即为最终的决定",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]