[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937894":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937894,606,1,"单选题","（2017年真题）根据《标准施工招标文件》 (2007 年版)，下列关于合同变更的说法错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人和监理人均可提出变更",false,{"key":16,"text":17,"correct":18},"B","发包人可直接向承包人发出变更指示",true,{"key":20,"text":21,"correct":14},"C","承包人收到经发包人签认的变更指示后，方可实施变更",{"key":23,"text":24,"correct":14},"D","若承包人认为变更指示不能执行，应立即说明理由","发包人和监理人均可以提出变更(注：承包人×， 承包人提出书面变更建议)。 变更指示只能由监理人发出，监理人发出变更指示前应征得发包人同意。承包人收到经发包人签认的变更指示后，方可实施变更。未经许可，承包人不得擅自对工程的任何部分进行变更。 承包人收到变更指示后，应按变更指示进行变更工作",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]