[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937893":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937893,606,1,"单选题","（2016年真题）下列关于工程隐蔽部位覆盖前的检查说法错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程隐蔽部位施工作业完成后，必须在覆盖前由承包人先行自检",false,{"key":16,"text":17,"correct":14},"B","工程隐蔽部位经监理人检查合格并签证后，才能进行下一道工序",{"key":19,"text":20,"correct":14},"C","承包人私自覆盖的工程，监理人有权指示承包人进行补检，无论结果如何，责任均由承包人承担",{"key":22,"text":23,"correct":24},"D","由发包人提供的材料或工程设备不合格造成的工程不合格的，由发包人采取补救措施",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]