[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},937837,606,1,"单选题","（2016年真题）自招标文件出售之日起至停止出售之日止，最短不得少于( )个工作日.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","15",{"key":23,"text":24,"correct":18},"D","20","新教材是不少于5日，而不是工作日。且20天是投标人编制标书的时间，而不是招标文件的出售时间！ @##",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]