[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937832,606,1,"单选题","（2013年真题）全职人员在项目团队中的比例达到五分之一、有专职项目经理的工程项目组织模式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目式模式",false,{"key":16,"text":17,"correct":18},"B","平衡矩阵模式",true,{"key":20,"text":21,"correct":14},"C","强矩阵式模式",{"key":23,"text":24,"correct":14},"D","弱矩阵式模式","本题考查的是项目管理组织结构的变化与组织结构的优化。平衡矩阵式要求全职人员在项目团队中的比例占15%～60%，有专职的项目经理的责任。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]