[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937829,606,1,"单选题","（2014年真题）项目团队的一些特殊人员必须按照委托方要求来设定岗位，这种人员配备方式属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","内部招聘",false,{"key":16,"text":17,"correct":14},"B","外部招聘",{"key":19,"text":20,"correct":21},"C","预安排",true,{"key":23,"text":24,"correct":14},"D","商谈","本题考查的是人员吸纳。项目委托方对项目人员有特殊要求，项目团队的一些特别人员必须按委托方要求来安排，这种方式为预安排。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]