[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937818":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937818,606,2,"多选题","（2014年真题）减少管理幅度对项目组织产生的影响主要有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","减少管理层次",false,{"key":16,"text":17,"correct":14},"B","减少用于协调的时间和费用",{"key":19,"text":20,"correct":21},"C","信息传递中易发生信息丢失",true,{"key":23,"text":24,"correct":21},"D","降低办事效率",{"key":26,"text":27,"correct":14},"E","减少对下属的监督时间","CD","减小管理幅度对组织的影响主要有： ①管理层次增加，相互之间的工作协调难度加大，为此所花费的时间与费用都会增加；②由于层次增加，信息的传递容易发生丢失和失真；③办事效率降低",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]