[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937814":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937814,606,2,"多选题","（2016年真题）项目雇员考核的作用包括( )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","及时发现问题",false,{"key":16,"text":17,"correct":18},"B","有利于加强成员的团队意识",true,{"key":20,"text":21,"correct":18},"C","时刻提醒成员要完成的任务",{"key":23,"text":24,"correct":18},"D","调动成员积极性",{"key":26,"text":27,"correct":18},"E","提高成员工作效率","BCDE","考核的作用 1.有利于加强成员的团队意识 2.时刻提醒团队成员要完成的任务 3.调动成员积极性 4.提高成员工作效率 5.保证项目目标的实现",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]