[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937788":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937788,606,2,"多选题","（2009年真题）项目经理在建立工作基础阶段的工作包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","编制项目工作计划",true,{"key":16,"text":17,"correct":14},"B","分析项目相关人员",{"key":19,"text":20,"correct":21},"C","组织制订具体实施计划",false,{"key":23,"text":24,"correct":14},"D","了解项目情况",{"key":26,"text":27,"correct":14},"E","研究工作任务","ABDE","项目工作计划主要包括以下几方面的内容： (1)项目名称。 (2)项目基本情况。 (3)项目团队工作目标与任务。 (4)项目工作进度计划。 (5)项目团队组成与分工。 (6)项目费用计划。 (7)成果的形式、成果交付数量、时间及交付方式。 (8)项目费用的来源",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]