[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937782":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937782,606,2,"多选题","（2011年真题）制约项目组织计划制订的主要因素包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目的组织结构",true,{"key":16,"text":17,"correct":18},"B","项目的融资方案",false,{"key":20,"text":21,"correct":14},"C","项目管理层的偏好",{"key":23,"text":24,"correct":14},"D","项目人员的预先安排",{"key":26,"text":27,"correct":18},"E","项目的质量标准","ACD","本题考查的是制定组织计划要注意的问题。制约项目团队组织的因素主要包括：（1）项目的组织结构；（2）共同达成的有关协议；（3）项目管理层的偏好；（4）预期的人员安排。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]