[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937780":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937780,606,2,"多选题","（2011年真题）关于编制项目工作计划的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","组织编制项目工作计划是项目经理的重要工作",true,{"key":16,"text":17,"correct":14},"B","项目工作计划是开展项目工作的规定性文件",{"key":19,"text":20,"correct":21},"C","项目工作计划的编制不受委托方影响",false,{"key":23,"text":24,"correct":21},"D","项目工作计划又称为项目工作大纲（TOR）",{"key":26,"text":27,"correct":14},"E","项目工作计划应包括项目工作进度计划","ABE","本题考查的是项目经理。实际工作中项目工作计划的主要内容往往在项目正式确定之前就明确下来了，在项目正式确定后，项目经理应尽快组织完成工作计划的正式文件，并与项目委托方取得一致意见。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]