[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937751,606,1,"单选题","(2012)对工程项目团队完成工作的进度与费用进行跟踪检查时，常用的管理工具是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直方图与决策树",false,{"key":16,"text":17,"correct":18},"B","横道图与网络图",true,{"key":20,"text":21,"correct":14},"C","网络图与鱼刺图",{"key":23,"text":24,"correct":14},"D","横道图与决策树","项目经理要经常进行进度跟踪。 在进行进度跟踪的同时，还要进行质量跟踪与费用跟踪。 具体方法可采用横道图、网络图等技术手段。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]