[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937731":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937731,606,1,"单选题","（2010年真题）进行工程项目组织内角色和职责安排，适宜使用的工具是( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作分解结构",false,{"key":16,"text":17,"correct":14},"B","网络图",{"key":19,"text":20,"correct":21},"C","责任分配矩阵",true,{"key":23,"text":24,"correct":14},"D","S曲线","项目角色和职责与项目范围的确定是紧密联系的。 责任分配矩阵通常就用于这一目的。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]