[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937729,606,1,"单选题","（2006年真题）在工程项目人力资源管理中，最为基础性的工作是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制人员配备计划",false,{"key":16,"text":17,"correct":14},"B","编制组织关系图表",{"key":19,"text":20,"correct":14},"C","雇员考核",{"key":22,"text":23,"correct":24},"D","进行工作分析",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]