[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937728,606,1,"单选题","（2011年真题）下列工作中，不属于工程项目组织计划工作的是( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定角色和职责",false,{"key":16,"text":17,"correct":14},"B","制订人员配备计划",{"key":19,"text":20,"correct":21},"C","确定项目管理模式",true,{"key":23,"text":24,"correct":14},"D","制订组织关系图","组织计划通常包括四方面的内容：角色和职责安排、人员配备计划、组织关系图和有关说明。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]