[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},937726,606,1,"单选题","（2016年真题）项目团队实现预定目标的关键是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将团队作为一个完整的整体来开发",true,{"key":16,"text":17,"correct":18},"B","提高参与项目个人的贡献力",false,{"key":20,"text":21,"correct":18},"C","提高项目团队的能力",{"key":23,"text":24,"correct":18},"D","使团队保持和发展工作动力","项目团队能力的开发包括两个方面：一是提高项目参与者个人的贡献力；二是提高项目团队整体能力。 个人能力在管理和技术方面的提高是项目团队发展的基础。 为了使项目团队能力满足项目要求， 团队作为一个完整的整体来开发是项目团队实现预定目标的关键。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]