[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937722,606,1,"单选题","（2012年真题）能够清晰反映团队成员与项目相关的所有活动和同每项活动相关的所有人员的管理工具是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织分解结构图",false,{"key":16,"text":17,"correct":18},"B","责任分配矩阵",true,{"key":20,"text":21,"correct":14},"C","资源分解结构图",{"key":23,"text":24,"correct":14},"D","角色—职责—职权表","本题考查的是团队组织计划。矩阵图能反映与每个人相关的所有活动以及与每项活动相关的所有人员。它也可以确保任何一项任务都只有一个人负责，从而避免混乱。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]