[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937713":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937713,606,2,"多选题","（2010年真题）建立工程项目目标系统时应作的主要工作有( )",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工程项目构思",true,{"key":16,"text":17,"correct":14},"B","识别需求",{"key":19,"text":20,"correct":14},"C","提出项目目标",{"key":22,"text":23,"correct":14},"D","建立目标系统",{"key":25,"text":26,"correct":27},"E","提出项目申请",false,"ABCD","工程项目目标系统的建立过程。 工程项目构思→识别需求→提出项目目标→建立目标系统",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]