[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937711":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937711,606,2,"多选题","（2008年真题）工程项目管理处于多种因素构成的复杂环境中，必须考虑( )等多方面的影响。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","上级组织",true,{"key":16,"text":17,"correct":18},"B","竞争对手",false,{"key":20,"text":21,"correct":14},"C","社会经济、文化、政治、法律",{"key":23,"text":24,"correct":18},"D","项目管理论的发展",{"key":26,"text":27,"correct":14},"E","标准规范和规程的约束","ACE","主要有如下因素： (1)上级组织的影响。 (2)社会、经济、文化、政治和法律等方面的影响。 (3)标准、规范和规程的约束",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]