[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},937699,606,1,"单选题","（2012年真题）国际标准化与国际咨询师联合会均推荐采用的项目过程管理方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划→实施→检查→处理",true,{"key":16,"text":17,"correct":18},"B","计划→指挥→监督→检查",false,{"key":20,"text":21,"correct":18},"C","指挥→监督→运转→协调",{"key":23,"text":24,"correct":18},"D","计划→沟通→指挥→协调","本题考查的是工程项目管理的基本原理。ISO 和FIDIC 推荐采用国际通用的PDCA（Plan－Do－Check－Act）循环方法，即计划→实施→检查→处理。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]