[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937698":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937698,606,1,"单选题","（2013年真题）工程项目组织系统由（ ）的人员、单位和部门构成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从事项目决策管理工作",false,{"key":16,"text":17,"correct":14},"B","从事政府相关管理工作",{"key":19,"text":20,"correct":21},"C","负责完成项目工作分解结构中各项工作",true,{"key":23,"text":24,"correct":14},"D","承担项目资金筹措任务","本题考查的是工程项目管理的基本原理。工程项目组织系统是由主要负责完成项目工作分解结构（WBS）中各项工作任务的个人、单位和部门所构成。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]