[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937697,606,1,"单选题","（2011年真题）关于 PDCA 循环的说法，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","PDCA是一个合乎逻辑的工作程序",false,{"key":16,"text":17,"correct":18},"B","PDCA的基本原理是目标系统管理",true,{"key":20,"text":21,"correct":14},"C","PDCA循环需要运行多次才能完成",{"key":23,"text":24,"correct":14},"D","PDCA呈阶梯式上升的趋势","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]