[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937691,606,1,"单选题","（2009年真题）在工程项目目标系统的建立过程中，进行工程项目环境分析是( )阶段的重要内容",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程项目构思",false,{"key":16,"text":17,"correct":14},"B","识别需求",{"key":19,"text":20,"correct":14},"C","工作结构分解",{"key":22,"text":23,"correct":24},"D","提出项目目标",true,"提出项目目标。通过对工程项目本身和工程项目环境的分析，确定需求目标。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]