[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},937686,606,1,"单选题","（2012年真题）工程项目准备阶段的工作不包括( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行可行性研究",true,{"key":16,"text":17,"correct":18},"B","编制项目概算",false,{"key":20,"text":21,"correct":18},"C","进行工程设计",{"key":23,"text":24,"correct":18},"D","签订承包合同","工程项目准备阶段 主要工作包括：工程项目的初步设计、 技术设计和施工图设计，工程项目征地及建设条件的准备，货物采购， 工程招标及选定承包商、签订承包合同等。 本阶段是战略决策的具体化，在很大程度上决定了工程项目实施的成败及能否高效率地达到预期目标。 工作重点是准备和安排项目所需建设条件，以工程项目开工建设为结束",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]