[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937684,606,1,"单选题","（2013年真题）某公司在境外投资建设的大型水电项目因当地原因不得不中止，使公司蒙受巨大损失。可见工程项目具有( )特征。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","一次性",false,{"key":16,"text":17,"correct":14},"B","独特性",{"key":19,"text":20,"correct":14},"C","目标明确性",{"key":22,"text":23,"correct":24},"D","复杂性",true,"工程项目的复杂性主要表现为：(1)工程项目交易及生产过程的复杂性。(2)工程项目组织的复杂性。(3)工程项目环境的复杂性。环境：国际国内政治局势、社会、经济、法律、文化。工程项目团队的上级组织和合作伙伴的组织，项目的建设条件和自然条件。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]