[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937681":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937681,606,1,"单选题","（2014年真题）从业主的角度看，传统的工程项目发包模式（设计—招标—建造模式）的主要优点是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计过程中较多考虑了可施工性",false,{"key":16,"text":17,"correct":14},"B","项目实施周期较短",{"key":19,"text":20,"correct":14},"C","设计方和施工方责任明确",{"key":22,"text":23,"correct":24},"D","施工阶段易于掌控设计变更",true,"本题考查的是工程项目的承发包管理模式。选项A 错误，对可施工性考虑不足；选项B 错误，实施周期较长；选项C 错误，设计与施工责任不明确，容易推诿责任。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]